Burtch Sanitary Trunk Upgrade

Home > Our community > Planning & projects > Current capital projects > Burtch Sanitary Trunk Upgrade

The Burtch Sanitary Trunk is a critical element of the City’s wastewater infrastructure and is currently in need of immediate repair due to hydrogen sulfide degradation within the existing concrete pipe. In order to upgrade the trunk, the City has opted to do so via a Cured-In-Place-Pipe (CIPP) lining program as the desired means of rehabilitation. Benefits of utilizing this trenchless technology include its modest cost compared to a traditional excavate and replace method, accelerated timeline to project completion as well as significantly reduced public disruption.

 

Tentative schedule of work tasks:

  • April 8 to 10 - Directional drill of north-end bypass pipe under Spall/Clement intersection. COMPLETE.
  • April 22 to 27 - North end bypass mobilization and temporary Rail Trail ramp setup. Rail Trail ramps will be setup adjacent Hardy Street and Vineland Street.
  • April 29 to May 17 - Lining of sewer trunk north of Hwy 97.
  • May 6 to 10 - Setup of temporary, shallow bury bypass sleeves along Burtch Rd under Sutherland Ave, Dickson Ave and Springfield Rd. 
  • May 13 to 17 - Setup of temporary road ramps over the bypass pipe at driveways for 1985 Burtch Rd, 1995 Burtch Rd, 2125 Burtch Rd (south driveway only), 2175 Burtch Rd, the northbound lanes of Burtch Rd adjacent Mill Creek as well as Byrns Rd just east of the roundabout. A temporary, shallow bury bypass sleeve for access to 2225 Burtch Rd is also planned this week. 
  • May 20 to 25 - South Hwy 97 bypass mobilization and setup. 
  • May 27 to June 8 - Lining of sewer trunk south of Hwy 97.
  • June 10 to June 22 - Removal of all ramps and shallow bury access points and reinstatement of existing roadways.
  • June 24 to 29 - Rehabilitation of site and demobilization.