Road report

Road information is based on issued road usage permits. All public and private contractors are required to obtain a road usage permit for work affecting traffic flow. Click on a coloured line on the map for details about traffic impacts. 

Subscribe to road report e-updates  

Permit number: RUP2021-0016
ALBERTA CT to JOHNSON RD
January 18, 2021 - 7:00am to December 31, 2021 - 5:00pm
No Disruption
JOHNSON RD to MANITOBA PL
January 18, 2021 - 7:00am to December 31, 2021 - 5:00pm
No Disruption
1360 Cornwall / 331 Lake Ave - big steel box parked on Cornwall for 2 days only then moved to Big Steel Box site and will keep on their site till the 11th then moved to 331 Lake Ave on the 11th for 2 days only. Gave them the weekly rate considering th
Permit number: RUP2021-0789
Phone: 250-869-4422
WATER ST to PANDOSY ST
October 28, 2021 (All day) to November 12, 2021 (All day)
No Disruption
CRIDGE RD to EAST END OF ROAD
October 28, 2021 (All day) to November 12, 2021 (All day)
No Disruption
230 Aurora Cres & 590 Hwy 33/[ Hollywood Rd (in Blvd) - install Shaw conduit and service boxes . Trenching is primarily in grass boulevard along Hollywood Rd. There will be soil stockpiled in the curb lanes as the works are being trenched in the grass a
Permit number: RUP2021-0734
HWY 33 W to HOLLYWOOD RD N
September 29, 2021 - 7:00am to October 29, 2021 - 5:00pm
Single Lane Alternating
Annual Permit - various city streets. Window & Sidewalk Cleaning
Permit number: RUP2021-0028
Project contact: Ashley Burnell
Phone: 250-864-7640
LAKESHORE RD to LANDIE RD
October 22, 2021 - 7:00am to December 31, 2021 - 4:00pm
No Disruption
LAKESHORE RD to LANFRANCO RD
October 22, 2021 - 7:00am to December 31, 2021 - 4:00pm
No Disruption
SWORDY RD to RICHTER ST
October 22, 2021 - 7:00am to December 31, 2021 - 4:00pm
No Disruption
Aurora Cres - Daytime road closure for moving equipment and material across Aurora Cres from our storage yard to our building site.
Permit number: RUP2021-0266
Project contact: Pamela Smith
Phone: 204-777-1972
HWY 33 W to HOLLYWOOD RD N
April 12, 2021 (All day) to December 31, 2021 (All day)
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
Aurora Cres 230 - Close sidewalk to errect a site fence. Signs to be placed on the west end of the sidewalk ending on the north side of the sidewalk. Pedestrians rerouted to sidewalk on other side of street. Map attached.
Permit number: RUP2021-0115
Project contact: Travis McQuigge
Phone: 204-777-1972
HWY 33 W to HOLLYWOOD RD N
August 19, 2021 (All day) to December 31, 2021 (All day)
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
HWY 33 W to HOLLYWOOD RD N
February 18, 2021 (All day) to December 31, 2021 (All day)
Beaver Lake Rd 350 - install 3 catch basins, install curb, gutter, sidewalks and asphalt restoration. Center of Beaver Lake Rd to access a manhole, then trenching to north shoulder across westbound lane intersection of Jim Bailey Rd and Beaver Lake Rd to
Permit number: RUP2021-0777
Project contact: Dan
Phone: 778-215-1649
JIM BAILEY RD to BEAVER LAKE CT
October 19, 2021 - 7:00am to November 12, 2021 - 6:00pm
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
Begbie Rd 1870 - big steel box on City Road Shoulder. Moving
Permit number: RUP2021-0792
Phone: 780-972-6691
UNION RD to HIDDEN HILLS DR
October 26, 2021 (All day) to November 12, 2021 (All day)
No Disruption
Bernard Ave 560-592 - demolition of building and erect 34 story & 16 story concrete high rises. Retail, parkade podium & residential. Sidewalk closure signs to be posted and to provide detour route for pedestrians.
Permit number: RUP2021-0054
Project contact: Nima Birzins
ST PAUL ST to BERTRAM ST
October 24, 2021 (All day) to October 30, 2021 (All day)
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
Black Mountain Dr - I have two signs R&L Excavated provided for us showing Sidewalk Closed. Im looking to pull a permit for one month, we wont be using it everyday, only days we need access with our genie to the front of the buildings. Please let
Permit number: RUP2021-0766
Project contact: Munny Panesar
LUND RD to STOCKLEY ST
October 12, 2021 - 7:00am to November 11, 2021 - 9:00pm
No Disruption
Calmels Cres 1053 - Telus need to do U/G drilling for a vault installation.
Permit number: RUP2021-0784
Project contact: Mattea Peterson
Phone: 250-617-7852
CALMELS CR to CALMELS CR
October 20, 2021 - 9:00am to October 31, 2021 - 5:00pm
Single Lane Alternating
Casorso Rd 3715 for 3642 Mission Springs Dr - create a drive isle entrance across sidewalk and create site line for road access to job site on Mission Springs Dr. Contractor has rented said property on 3715 Casorso for $75,000 from the City. Only access
Permit number: RUP2021-0240
Project contact: Myk Detmers
Phone: 250-862-0207
MISSION SPRINGS DR to BARRERA RD
April 15, 2021 (All day) to December 31, 2021 (All day)
No Disruption
Cawston Ave 660 - construction of condos. Water, sewer, storm, and asphalt installs and paved.
Permit number: RUP2021-0179
Project contact: Julia Hansum
BERTRAM ST to RICHTER ST
March 20, 2021 (All day) to October 31, 2021 (All day)
Local Traffic Only, No Through Traffic, Detour
BERTRAM ST to RICHTER ST
March 19, 2021 (All day) to December 31, 2021 (All day)
Local Traffic Only, No Through Traffic, Detour
City of Kelowna Project - Washing and Inspecting intersection Lights
Permit number: RUP2021-0166
LAKESHORE RD to ELDORADO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to ELDORADO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GORDON DR to DEHART RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GORDON DR to DEHART RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SARSONS RD to DEHART RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GLENMORE RD to CROSS RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
VALLEY RD to SUMMIT DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUMMIT DR to GLENMORE DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUMMIT DR to GLENMORE DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
YATES RD to GLENMORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
YATES RD to GLENMORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
CLIFTON RD to CARA GLEN WAY
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
MOUNTAIN AVE to CLIFTON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LYNWOOD CR to CLIFTON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LYNWOOD CR to CLIFTON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KENNEDY ST to HIGH RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KENNEDY ST to HIGH RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
VALLEY RD to SUMMIT DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to LEON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LEON AVE to ELLIS ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to BENVOULIN RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to DAYTON ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to CADDER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to CADDER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to BURTCH RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to RICHTER ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RAYMER AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ROSE AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ROSE AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ROYAL AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ROYAL AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
JOHN HINDLE DR to GLENMORE RD N
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LECKIE RD to BARON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ENTERPRISE WAY to DILWORTH DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ENTERPRISE WAY to COOPER RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
HARDY ST to ENTERPRISE WAY
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to ETHEL ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to ETHEL ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GORDON DR to CAWSTON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WATER ST to CLEMENT AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WATER ST to CLEMENT AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to DURNIN RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to LECKIE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to CLEMENT AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to CLEMENT AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RUTLAND RD N to LEATHEAD RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
MOUNTAIN AVE to GLENMORE DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
MOUNTAIN AVE to GLENMORE DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
MOUNTAIN AVE to CLIFTON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
UPPER CAMPUS WAY to ACADEMY WAY
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
UPPER CAMPUS WAY to ACADEMY WAY
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ELLIS ST to DOYLE AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ELLIS ST to DOYLE AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
HWY 33 W to ENTERPRISE WAY
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GORDON DR to CLEMENT AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ROSE AVE to RICHTER ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to NEPTUNE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to CEDAR AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RAYMER AVE to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RAYMER AVE to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to RAYMER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to RAYMER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RAYMER AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
OLD MEADOWS RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
OLD MEADOWS RD to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to ARMOUR CR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LEQUIME RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LEQUIME RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to CEDAR AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUMMIT DR to DILWORTH DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUMMIT DR to DILWORTH DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RUTLAND RD N to MCCURDY RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
CLIFTON RD to CARAMILLO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GORDON DR to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ETHEL ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
HOUGHTON RD to HOLLYWOOD RD N
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to CAWSTON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to CAWSTON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ELLIS ST to CAWSTON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAWRENCE AVE to ELLIS ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to LAWRENCE AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to LAWRENCE AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ZIPRICK RD to SPRINGFIELD RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to PANDOSY ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to CADDER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to CADDER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to GERSTMAR RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to SPALL RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GUISACHAN RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to HOLLYWOOD RD S
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to COOPER RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
CLIFTON RD to CLEMENT AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LANFRANCO RD to BOTHE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LANFRANCO RD to BOTHE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to BARRERA RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to BARRERA RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
UNION RD to GLENMORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
UNION RD to GLENMORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
UNION RD to SNOWSELL ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
UNION RD to SNOWSELL ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPALL RD to CLEMENT AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ROSE AVE to RICHTER ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ELLIS ST to CAWSTON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
CLEMENT AVE to CERISE DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WELKE RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WELKE RD to DEL MONTE ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WELKE RD to DEL MONTE CT
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SHORT RD to HOBSON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to HOBSON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
OLD MEADOWS RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
TUTT ST to KLO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
TUTT ST to KLO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
STEELE RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
STEELE RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PARET PL to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
DEL MONTE ST to DEL MONTE CT
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to DE MONTREUIL CT
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to CADDER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to CADDER AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPRINGFIELD RD to BURTCH RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GORDON DR to CASORSO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GORDON DR to CASORSO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
BYRNS RD to BENVOULIN RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GUISACHAN RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LEXINGTON DR to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LEXINGTON DR to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
TRUSWELL RD to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
TRUSWELL RD to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to DE MONTREUIL CT
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to CASORSO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to CASORSO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to KLO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to KLO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to BENVOULIN RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to BENVOULIN RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KLO RD to GORDON DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LOWE CT to KLO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LOWE CT to KLO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WILLMS RD to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WILLMS RD to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SARSONS RD to DEHART RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WATER ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WATER ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
QUEENSWAY to ELLIS ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
QUEENSWAY to ELLIS ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ENTERPRISE WAY to BANKS RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
BERTRAM ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ST PAUL ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ST PAUL ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ELLIS ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
ELLIS ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to COOK RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to COOK RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SHEPHERD RD to RUTLAND RD N
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LEATHEAD RD to HOLLYWOOD RD N
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SCENIC RD to GLENMORE RD N
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SCENIC RD to GLENMORE RD N
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GLENMORE RD N to BEGBIE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
GLENMORE RD N to BEGBIE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KANE RD to DRYSDALE BLVD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KANE RD to DRYSDALE BLVD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KANE RD to BALLOU RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
KANE RD to BALLOU RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SEXSMITH RD to CAMBRO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAWRENCE AVE to ABBOTT ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAWRENCE AVE to ABBOTT ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
BURTCH RD to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LEON AVE to ELLIS ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to LEON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
PANDOSY ST to LEON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WATER ST to LEON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
WATER ST to LEON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAWRENCE AVE to ELLIS ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SUTHERLAND AVE to RICHTER ST
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
HARVEY AVE to DILWORTH DR
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
HARVEY AVE to COOPER RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to LEON AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to LANFRANCO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to LANFRANCO RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LANFRANCO RD to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LANFRANCO RD to LAKESHORE RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to BARNABY RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to CRIGHTON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to CRIGHTON RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
RICHTER ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
BERTRAM ST to BERNARD AVE
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPALL RD to ENTERPRISE CT
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
SPALL RD to ENTERPRISE CT
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LECKIE RD to ENTERPRISE WAY
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
BARON RD to BANKS RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LECKIE RD to HUNTER RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
LAKESHORE RD to BARNABY RD
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
JOHN HINDLE DR to GLENMORE RD N
March 15, 2021 - 9:00am to December 20, 2021 - 3:30pm
Continually Moving Work
Continue Project
Permit number: RUP2020-0057
Project contact: Kameran Hussein
Phone: 250-718-7694
BERNARD AVE to DOYLE AVE
May 3, 2020 (All day) to November 30, 2021 (All day)
ELLIS ST to ST. PAUL ST
May 3, 2020 (All day) to November 30, 2021 (All day)
Dehart Ave 984 - line painting, pour letdowns, pour sidewalks, boulevards (when design received).
Permit number: RUP2021-0768
Project contact: Dustin Dobbin
Phone: 250-862-6905
WESTPOINT DR to BARTHOLOMEW CT
October 9, 2021 - 7:00am to October 28, 2021 - 5:00pm
Single Lane Alternating
Dickson Ave 1640/1700 - Unloading Construction Material Periodic Intermittent 20 min closures
Permit number: RUP2020-0308
Project contact: Ryan Seddon
DAYTON ST to KIRSCHNER RD
January 1, 2020 (All day) to December 31, 2021 (All day)
Local Traffic Only, Detour, Emergent Work, Business Open
Dilworth Dr 1975 & 1945 - storm, sanitary, watermain install. Lane widening and traffic signal upgrades, additional shallow utilities to follow for Fortis, Telus & Shaw once NTP received for each separate Utility.
Permit number: RUP2021-0470
Project contact: Marlon Hall
Phone: 604-845-3185
BENVOULIN RD to BARON RD
June 19, 2021 (All day) to December 31, 2021 (All day)
Lane Drop - Multi Lane Road
DILWORTH DR to UNDERHILL ST
June 19, 2021 (All day) to December 31, 2021 (All day)
Lane Drop - Multi Lane Road
Ellis St 1265/Coronation Ave & Back Lane) install new aterline, sanitary, storm services from building to City property. COK doing tie-in
Permit number: RUP2021-0717
Project contact: Shelley/ Jason
Phone: 250-809-2415
ELLIS ST to ST PAUL ST
September 23, 2021 - 7:00am to November 30, 2021 - 4:30pm
Lane Drop - Multi Lane Road
CAWSTON AVE to CORONATION AVE
September 23, 2021 - 7:00am to November 30, 2021 - 4:30pm
Lane Drop - Multi Lane Road
Enterprise Way 1925 - all previous work completed. Landscape boulevard. Plants, trees and top soil.
Permit number: RUP2021-0711
Project contact: Jon Bahry
Phone: 250-300-5072
ENTERPRISE WAY to CLEMENT AVE
September 20, 2021 - 8:00am to October 29, 2021 - 3:30pm
Lane Drop - Multi Lane Road
SPALL RD to HARDY ST
September 20, 2021 - 8:00am to October 29, 2021 - 3:30pm
Lane Drop - Multi Lane Road
Field Rd & McCulloch Rd Water Improvements. Purchasing Notice to Proceed attached.
Permit number: RUP2021-0673
Project contact: Darren Trozzo
Phone: 250-718-569
MCCULLOCH RD to NORTH END OF ROAD
September 8, 2021 - 7:00am to October 29, 2021 - 3:00pm
Single Lane Alternating
FIELD RD to CITY LIMIT
September 8, 2021 - 7:00am to October 29, 2021 - 3:00pm
Single Lane Alternating
SOUTH END OF ROAD to MCCULLOCH RD
September 8, 2021 - 7:00am to October 29, 2021 - 3:00pm
Single Lane Alternating
Finns Rd 820 - pull in new underground cables. All previous excavation work done by separate contractor.
Permit number: RUP2021-0002
Project contact: Dustin Bates
Phone: 250-717-0828
DEAD END to ETHEL ST
January 21, 2021 - 8:30am to December 21, 2021 - 4:30pm
Local Traffic Only
PINEGROVE RD to SWAISLAND RD
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
HOBSON CR to HOBSON CR
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
ULEY RD to SHORT RD
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
HOBSON CR to ULEY RD
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
HOBSON CR to PINEGROVE RD
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
SARSONS RD to SARSONS RD
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
SWAISLAND RD to SARSONS RD
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
SWAISLAND RD to DEHART RD
October 6, 2021 - 7:00am to November 30, 2021 - 3:00pm
No Disruption
Fitzpatrick Rd 729 - install Fortis conduit and service box on shoulder of road to service address.
Permit number: RUP2021-0798
Project contact: Dan Padmorow
Phone: 778-215-1649
FINNS RD to FINDLAY RD
October 28, 2021 - 7:00am to October 29, 2021 - 5:00pm
Single Lane Alternating
Fortis Weekly Service Installs -
Permit number: RUP2021-0793
Project contact: Thomas Abenante
Phone: 250-868-4518
POPLAR RD to DOEKSEN RD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
RICHTER ST to ETHEL ST
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
RICHTER ST to ETHEL ST
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
LAKE AVE to RIVERSIDE AVE
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
FROST RD to BARNABY RD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
RICHTER ST to ETHEL ST
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
SOUTH END OF ROAD to MOUNTAINSIDE DR
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
RICHTER ST to ETHEL ST
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
FRANCIS AVE to BIRCH AVE
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
MINE HILL DR to EAST END OF ROAD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
STEELE RD to EAST END OF ROAD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
GREY OWL CT to HILLTOWN DR
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
LESTER RD to O'KEEFE CT
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
SOUTH END OF ROAD to CARA GLEN WAY
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
LOCHNESS ST to CARNEGIE ST
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
BURTCH RD to BENVOULIN RD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
GARNER RD to TEASDALE RD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
LARK ST to EAST END OF ROAD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
RUBY RD to DIAMOND RD
October 25, 2021 - 7:00am to October 29, 2021 - 5:00pm
No Disruption
Fuller Ave 555 - Road closure for a 68 unit apartment building. Hoarding/closure permit for Fuller Ave for the duration of the project. Closure of the side sidewalk on Bertram to be temporarily located on the shoulder of Bertram as requested by the Legion
Permit number: RUP2021-0230
Project contact: Rob VandenPol
Phone: 250-487-8342
WEST END OF ROAD to BERTRAM ST
April 19, 2021 (All day) to December 31, 2021 (All day)
Full Road Closure, Local Traffic Only, No Through Traffic, Detour, Business Open
Grigg Rd (All Road) - dead end road off of Jim Bailey & Bubna Rd. Install Fortis conduit
Permit number: RUP2021-0780
Project contact: Randy Frasch
Phone: 250-212-0010
SOUTH END OF ROAD to BUBNA RD
October 18, 2021 - 7:30am to October 29, 2021 - 4:00pm
No Disruption
Hardy St 1500 - urgent repair to broken pipe near west corner of Hardy St. If pipe not found might have to go across Hardy down sidewalk across Enterprise.
Permit number: RUP2021-0794
Project contact: Randy Frasch
Phone: 250-212-0010
SPALL RD to HARDY ST
October 25, 2021 - 7:30am to November 5, 2021 - 4:00pm
Single Lane Alternating
ENTERPRISE WAY to NORTH END OF ROAD
October 25, 2021 - 7:30am to November 5, 2021 - 4:00pm
Single Lane Alternating
Hidden Hills (Wilden) & Union Rd bet Upper Canyon Ridge and Begbie Rd - Pre locates of existing Utilities along excavation part of future. Hydro-vacing potholes.
Permit number: RUP2021-0790
Project contact: Allan Sirett
Phone: 250-878-7861
BEGBIE RD to UPPER CANYON DR N
October 25, 2021 - 7:00am to October 28, 2021 - 5:00pm
No Disruption
BEGBIE RD to HIDDEN RIDGE PL
October 25, 2021 - 7:00am to October 28, 2021 - 5:00pm
No Disruption
HIDDEN RIDGE PL to TWIN RIDGE CT
October 25, 2021 - 7:00am to October 28, 2021 - 5:00pm
No Disruption
TWIN RIDGE CT to NORTH END OF ROAD
October 25, 2021 - 7:00am to October 28, 2021 - 5:00pm
No Disruption
Hilltown Dr 3778 N/B & S/B - Cut and remove high back curb, prep for new let down curb.
Permit number: RUP2021-0788
Project contact: Felix Menu
Phone: 778-212-3004
MCKINLEY BEACH DR to GLENMORE RD N
October 27, 2021 - 7:00am to November 5, 2021 - 5:00pm
Single Lane Alternating
Hollywood Rd 191 (SoHo Project) & Petch Rd - Install drywell, Connect to Existing sanitary manhole and install watermain. This area of Petch Rdis slated for offsite improvements as part of the project. We are proposing to leave the disturbed area as mi
Permit number: RUP2021-0320
Phone: 250-765-0330
BALMORAL RD to DELL RD
May 3, 2021 - 7:00am to October 30, 2021 - 5:00pm
Local Traffic Only, No Through Traffic, Detour
ARGYLL RD to HWY 33 W
May 3, 2021 - 7:00am to October 30, 2021 - 5:00pm
Local Traffic Only, No Through Traffic, Detour
Jim Bailey Rd 8900 - Please see attached plan, permit and Shaw/Fortis NTP's. Crafted Development will be digging a Trench for Shaw and Fortis Electric. They will be doing this work at 8900 Jim Bailey Rd. They would like to complete this work fr
Permit number: RUP2021-0750
Project contact: Mitch Wilde
HIRAM WALKER CT to JIM BAILEY CR
October 11, 2021 - 7:00am to November 5, 2021 - 6:00pm
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
Lakeshore Rd (bet Collett & Keith) - new multi-use path bridge and vehicle bridge improvements
Permit number: RUP2021-0127
Project contact: Mehrdad Shekerfkar - Project MANAGER
Phone: 604-330-2200
COLLETT RD to KEITH RD
October 21, 2021 - 7:00am to November 4, 2021 - 5:00pm
Lane Drop - Multi Lane Road
Lakeshore Rd 3795 - install sewer, water, storm services and remediations. Lakeshore Rd closed slight pattern change detour around work site.
Permit number: RUP2021-0731
Project contact: Rob Desjardin
Phone: 250-826-8876
COOK RD to BARRERA RD
September 28, 2021 - 9:00am to November 5, 2021 - 3:30pm
Detour, Lane Drop - Multi Lane Road
Lawrence Ave 540 - erect new building. Shut down sidewalk and move pedestrians into the 3 parking spaces infront of building. Sidewalk closure signs to be posted and parking meter bags to be purchased thru Kelowna Park.
Permit number: RUP2020-0423
Project contact: Vic Worman
ELLIS ST to BERTRAM ST
September 15, 2020 (All day) to October 30, 2021 (All day)
Local Traffic Only, Lane Drop - Multi Lane Road
Main St 5300 & Chute Lake Rd - all previous work completed. Going back to complete remainder of work. Tie-in hydrant and water line. 2 hot taps, tie-in to storm barrel on Main St along parking lane & shoulder. No sidewalk.
Permit number: RUP2021-0738
Project contact: Karlee Bremner
MCCARREN AVE to CHUTE LAKE RD
September 29, 2021 - 7:00am to October 29, 2021 - 5:00pm
Lane Drop - Multi Lane Road
LAKEPOINTE DR to MAIN ST
September 29, 2021 - 7:00am to October 29, 2021 - 5:00pm
Lane Drop - Multi Lane Road
McIntosh Rd & Froelich Rd - road Grinding of asphalt for 200 meters of watermain installation complete with Road Restoration for RWW. Work includes supply and place of new road gravels, curbing and sidewalk panel replacement plus 2 new hydrants installs
Permit number: RUP2021-0732
Project contact: Norman Stewart
Phone: 250-878-8006
DOUGALL RD N to MCINTOSH RD
October 18, 2021 (All day) to November 1, 2021 (All day)
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
FROELICH RD to DOUGALL RD N
October 4, 2021 (All day) to November 1, 2021 (All day)
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
Midtown Dilworth Dr 1975/1945 - Sidewalk closure required on Dilworth Dr for construction of individual multi family buildings.
Permit number: RUP2021-0771
Project contact: Jared Krish
Phone: 778-990-4540
BENVOULIN RD to BARON RD
June 19, 2021 (All day) to December 31, 2021 (All day)
No Disruption
Mountainside Dr 5533 - all previous work completed. Stu signed off on it. Grinding the edges so the top lift paving can be completed. Small curb to go in and clean up around area.
Permit number: RUP2021-0776
Project contact: Jacob
Phone: 250-864-4339
TRESTLE RIDGE DR to RINDLE CT
October 18, 2021 - 7:00am to October 29, 2021 - 5:00pm
Single Lane Alternating
New Costco Site - Springield, Baron, Durnin & Underhill
Permit number: RUP2021-0477
Project contact: Rob Reitman
Phone: 250-862-6720
HWY 97 N to BARON RD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
HAYNES RD to BARON RD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
UNDERHILL ST to EAST END OF ROAD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
BENVOULIN RD to DURNIN RD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
SPRINGFIELD RD to BARON RD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
BARON RD to PARKVIEW CR
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
LECKIE RD to SPRINGFIELD RD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
UNDERHILL ST to DURNIN RD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
PARKVIEW CR to SPRINGFIELD RD
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
WEST END OF ROAD to UNDERHILL ST
July 19, 2021 - 7:00am to October 29, 2021 - 5:30pm
Lane Drop - Multi Lane Road
Overhead & Non-Excavation Work Only - not including pole replacements. Traffic Impedance Only
Permit number: RUP2021-0012
Project contact: Darren Langford
Phone: 250-859-0349
DICKSON AVE to HARVEY AVE
October 10, 2021 - 8:00am to October 29, 2021 - 3:00pm
Single Lane Alternating
DAYTON ST to KIRSCHNER RD
October 10, 2021 - 8:00am to October 29, 2021 - 3:00pm
Single Lane Alternating
HIRAM WALKER CT to JIM BAILEY CR
October 28, 2021 (All day) to November 12, 2021 (All day)
Single Lane Alternating
Paving Projects for City of Kelowna Construction Crew -
Permit number: RUP2021-0213
Project contact: Kim Johnson
CLEMENT AVE to WEDDELL PL
October 28, 2021 - 7:00am to November 5, 2021 - 5:00pm
Lane Drop - Multi Lane Road
Raymer Ave West of Ethel and adjoining laneway on South side - install water line and water service. Good afternoon, Here is the road usage permit and TMP for work being done on Raymer Ave and a connecting Laneway. We will start Sept 15th and go
Permit number: RUP2021-0656
Project contact: Kaitline Stafford
Phone: 250-540-2441
KLO RD to RICHTER ST
September 15, 2021 - 7:00am to November 5, 2021 - 5:30pm
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
RICHTER ST to CURTS ST
September 15, 2021 - 7:00am to November 5, 2021 - 5:30pm
Full Road Closure, Local Traffic Only, No Through Traffic, Detour
Reid Rd 3257 - Install gas main in the boulevard to service address.
Permit number: RUP2021-0797
Project contact: Thomas Abenante
Phone: 250-868-4518
POOLEY RD to EAST KELOWNA RD
October 27, 2021 - 7:00am to November 1, 2021 - 4:00pm
Single Lane Alternating
Rutand Rd N 2100/Rutland Crt/Old Vernon Rd & Commerical Dr - install new services including mainlines for a commercial development, adding signas and turn lanes, bus pad on Rutland Rd, curb, gutter and sidewalk. Paving.
Permit number: RUP2021-0435
Phone: 250-808-8052
COMMERCIAL DR to NORTH END OF ROAD
June 9, 2021 (All day) to October 31, 2021 (All day)
CORNISH RD to COMMERCIAL DR
June 9, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
CORNISH RD to COMMERCIAL DR
June 9, 2021 (All day) to October 31, 2021 (All day)
LANDSDOWNE PL to RUTLAND CT
June 9, 2021 (All day) to October 31, 2021 (All day)
COMMERCIAL DR to OLD VERNON RD
June 9, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
COMMERCIAL DR to OLD VERNON RD
June 9, 2021 (All day) to October 31, 2021 (All day)
RUTLAND CT to RUTLAND RD N
June 9, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
SEXSMITH RD to ACLAND RD
June 9, 2021 - 9:00am to November 20, 2021 - 3:30pm
Single Lane Alternating
LANDSDOWNE PL to RUTLAND CT
June 9, 2021 - 9:00am to November 20, 2021 - 3:30pm
Single Lane Alternating
COMMERCIAL DR to NORTH END OF ROAD
June 9, 2021 - 9:00am to November 20, 2021 - 3:30pm
Single Lane Alternating
CORNISH RD to COMMERCIAL DR
June 9, 2021 - 9:00am to November 20, 2021 - 3:30pm
Single Lane Alternating
COMMERCIAL DR to OLD VERNON RD
June 9, 2021 - 9:00am to November 20, 2021 - 3:30pm
Single Lane Alternating
RUTLAND CT to RUTLAND RD N
June 9, 2021 - 9:00am to November 20, 2021 - 3:30pm
Single Lane Alternating
SEXSMITH RD to ACLAND RD
June 9, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
SEXSMITH RD to ACLAND RD
June 9, 2021 (All day) to October 31, 2021 (All day)
LANDSDOWNE PL to RUTLAND CT
June 9, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
RUTLAND CT to RUTLAND RD N
June 9, 2021 (All day) to October 31, 2021 (All day)
COMMERCIAL DR to NORTH END OF ROAD
June 9, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
Sept 29, 2021 Addition - blocking sidewalk, pedestrian traffic can cross at walkway on Harvey Ave on Abbott . Abbott St 1781 - Storm Install (offsite) Single lane alternating on Abbott for Sept 16th and 17th with flaggers. The rest of the time com
Permit number: RUP2021-0697
Project contact: Rob Zuest
Phone: 250-258-7738
ABBOTT ST to WATER ST
October 16, 2021 - 7:00am to November 5, 2021 - 5:00pm
No Disruption
St Paul St 1471 - install curb, sidewalk, top lift asphalt, letdowns and landscape paving stones.
Permit number: RUP2021-0770
Project contact: Vicky Bachelder
Phone: 250-870-0776
BERNARD AVE to DOYLE AVE
October 18, 2021 - 7:00am to November 6, 2021 - 5:00pm
Single Lane Alternating
Sunset/Water/Ellis St - Complete Project
Permit number: RUP2021-0596
Project contact: Kyle MacKay
Phone: 250-808-2236
WATER ST to GUY ST
August 6, 2021 (All day) to December 31, 2021 (All day)
No Disruption
CLEMENT AVE to GASTON AVE
August 6, 2021 (All day) to December 31, 2021 (All day)
No Disruption
SUNSET DR to CLEMENT AVE
August 6, 2021 (All day) to December 31, 2021 (All day)
No Disruption
Thalia St 5249 - big steel box on City road shoulder
Permit number: RUP2021-0772
Phone: 1-780-298-1244
QUILCHENA DR to ALLENBY LANE
October 15, 2021 (All day) to October 31, 2021 (All day)
No Disruption
Upper Mission Dr S/B & N/B - Trestle Ridge Phase 3 - Install Sanitary, Storm & Water
Permit number: RUP2021-0759
Project contact: Jason Bennett
Phone: 250-870-2405
SOUTH END OF ROAD to THE EDGE PL
October 12, 2021 - 7:00am to October 29, 2021 - 5:00pm
Single Lane Alternating
THE EDGE PL to TRESTLE RIDGE DR
October 12, 2021 - 7:00am to October 29, 2021 - 5:00pm
Single Lane Alternating
TRESTLE RIDGE CT to UPPER MISSION DR
October 12, 2021 - 7:00am to October 29, 2021 - 5:00pm
Single Lane Alternating
TRESTLE RIDGE DR to REDTAIL CT
October 12, 2021 - 7:00am to October 29, 2021 - 5:00pm
Single Lane Alternating
Various City Streets - City Contract for maintenance of the road planted meridians & sidewalks. Horticultural Maintenance.
Permit number: RUP2021-0145
Project contact: Tim Marshall
KLO RD to FISHER RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
COOPER RD to MAYER RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
CROSS RD to UNION RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
GLENMORE RD to SCENIC RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
FISHER RD to MUNSON RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
MUNSON RD to BEETLESTONE DR
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
RISSO RD to PIONEER RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
PIONEER RD to RAMPONE RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
QUILCHENA DR to FARRON PL
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
GLENMEADOWS RD to YATES RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
GLENMORE DR to GLENMEADOWS RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
SOUTH PERIMETER WAY to LAKEPOINTE DR
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
CHAMBERLAIN RD to KLO RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
RAMPONE RD to CHAMBERLAIN RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
DAYTON ST to KIRSCHNER RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
KIRSCHNER RD to SPALL RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
BEETLESTONE DR to BYRNS RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
BYRNS RD to COOPER RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
FARRON PL to CHUTE LAKE RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
DALLAS RD to CROSS RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
YATES RD to WATSON RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
GORDON DR to HOY ST
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
HOY ST to WILKINSON ST
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
WILKINSON ST to INKAR RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
INKAR RD to BURTCH RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
BURTCH RD to DAYTON ST
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
CLARANCE AVE to FROST RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
FROST RD to STEELE RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
PONDS AVE to CLARANCE AVE
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
WATSON RD to BALLOU RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
BALLOU RD to DALLAS RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
MAYER RD to SPRINGFIELD RD
March 8, 2021 - 9:00am to October 31, 2021 - 3:30pm
Lane Drop - Multi Lane Road
Various City Streets - tree trimming and tree removal services.
Permit number: RUP2021-0047
Project contact: Tony Wilkinson
Phone: 250-862-0734
PINTO RD to ADAMS RD
January 21, 2021 - 9:00am to December 31, 2021 - 3:30pm
No Disruption
MANHATTAN DR to EAST END OF ROAD
September 22, 2021 - 11:30am to December 31, 2021 - 4:00pm
No Disruption
Various Parks Work - various City streets
Permit number: RUP2021-0055
FROST RD to DEVONIAN AVE
October 19, 2021 - 8:30am to December 31, 2021 - 3:00pm
Single Lane Alternating
FROST RD to DEVONIAN AVE
October 19, 2021 - 8:30am to December 31, 2021 - 3:00pm
Single Lane Alternating
DEVONIAN AVE to ARBOR VIEW DR
October 19, 2021 - 8:30am to December 31, 2021 - 3:00pm
Single Lane Alternating
DEVONIAN AVE to ARBOR VIEW DR
October 19, 2021 - 8:30am to December 31, 2021 - 3:00pm
Single Lane Alternating
Water & Sanitary Sewer main Install - Ellis St from Cawston Ave to Clement Ave
Permit number: RUP2021-0712
Project contact: Steve Neetz
CAWSTON AVE to CORONATION AVE
September 27, 2021 - 12:00am to November 15, 2021 - 11:30pm
Full Road Closure, Detour
CORONATION AVE to CANNERY LANE
September 27, 2021 - 12:00am to November 15, 2021 - 11:30pm
Full Road Closure, Detour
CANNERY LANE to CLEMENT AVE
September 27, 2021 - 12:00am to November 15, 2021 - 11:30pm
Full Road Closure, Detour
Water St 1580 & 1570 - Demolish building and construct new building. Hoarding required on Lawrence, lane and Water St
Permit number: RUP2020-0531
Project contact: Slava Korshunov
LAWRENCE AVE to LANE
November 2, 2020 (All day) to December 31, 2021 (All day)
No Disruption
ABBOTT ST to WATER ST
November 2, 2020 (All day) to December 31, 2021 (All day)
No Disruption
Weddell/Ethel - Traffic Control Training
Permit number: RUP2021-0067
Project contact: Alex Johnson
CROWLEY AVE to BAY AVE
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
CROWLEY AVE to ETHEL ST
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
RICHTER ST to CROWLEY AVE
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
ETHEL ST to TRENCH PL
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
RICHTER ST to ETHEL ST
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
WEDDELL PL to ETHEL ST
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
VAUGHAN AVE to BAILLIE AVE
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
WEDDELL PL to CROWLEY AVE
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
BAILLIE AVE to RECREATION AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
BAILLIE AVE to RECREATION AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
RECREATION AVE to WEDDELL PL
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
RECREATION AVE to WEDDELL PL
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
VAUGHAN AVE to BAILLIE AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
RICHTER ST to ETHEL ST
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
RICHTER ST to ETHEL ST
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
ETHEL ST to TRENCH PL
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
ETHEL ST to TRENCH PL
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
CROWLEY AVE to BAY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
RICHTER ST to CROWLEY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
CROWLEY AVE to ETHEL ST
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
CROWLEY AVE to ETHEL ST
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
CROWLEY AVE to ETHEL ST
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
ETHEL ST to GORDON DR
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
RICHTER ST to CROWLEY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
BAILLIE AVE to RECREATION AVE
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
WEDDELL PL to ETHEL ST
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
RECREATION AVE to WEDDELL PL
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
WEDDELL PL to ETHEL ST
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
RICHTER ST to ETHEL ST
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
VAUGHAN AVE to BAILLIE AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
WEDDELL PL to ETHEL ST
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
CROWLEY AVE to BAY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
VAUGHAN AVE to BAILLIE AVE
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
WEDDELL PL to CROWLEY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
WEDDELL PL to CROWLEY AVE
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
WEDDELL PL to CROWLEY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
ETHEL ST to BAILLIE AVE
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
WEDDELL PL to ETHEL ST
October 28, 2021 -
8:00am to 4:30pm
Single Lane Alternating
ETHEL ST to CROWLEY AVE
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
ETHEL ST to CROWLEY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
ETHEL ST to CROWLEY AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
ETHEL ST to BAILLIE AVE
August 22, 2021 - 8:00am to December 31, 2021 - 4:30pm
Single Lane Alternating
ETHEL ST to BAILLIE AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating
ETHEL ST to BAILLIE AVE
October 3, 2021 - 8:00am to December 31, 2021 - 4:00pm
Single Lane Alternating