Starting May 16 construction along Airport Way from Old Vernon Road to Aerospace Drive will take place. Vehicles arriving to the airport from the North Okanagan are encouraged to use the main entrance at the lights. Traffic off Old Vernon Road along Airport Way may experience slight delays. This project is expected to be completed by mid November. What are we constructing? Underground works storm drywells and catch basins utilities, including street light ducting and Fortis connections road structure Surface works asphalt pavement - curb and gutter landscaping, tree planting sidewalks bus shelters streetlights benches - so you can watch aircraft landings and takeoffs
Underground works storm drywells and catch basins utilities, including street light ducting and Fortis connections road structure
Surface works asphalt pavement - curb and gutter landscaping, tree planting sidewalks bus shelters streetlights benches - so you can watch aircraft landings and takeoffs
May 16 to November 2011- Completed on time & on budget Design Consultant: EBA Engineering Contractor: City of Kelowna Cost: $4.3 million
For more information on the Airport Way Multi-Use Corridor project, please contact: airport@kelowna.ca Henry Castorf Airport Development Manager 250-765-5125 ext 210 Jenelle Hynes Airport Communications 250-765-5125 ext 207