Infrastructure projects

We're working to create vibrant urban centres, a balanced transportation network and an inclusive community. Infrastructure projects improve and maintain outdoor spaces, buildings, active transportation networks, utilities, roads and bridges. Navigate through the map below, or filter by project type, to find out what's happening in your community.

Subscribe to project e-updates   

Upgrading of the existing 350 mm sanitary forcemain that connects the Gyro Sanitary Lift Station to the Wastewater Treatment Facility for

Est. cost: $3.3 million
Est. start: Fall 2019
Est. end: Summer 2020

Full width repaving.

1.8 metre wide concrete sidewalk on the west side of Hollywood Road, from Hollydell Road to Highway 33, approximately 560 metres in lengt

Est. cost: $260,000
Est. start: Fall 2018
Est. end: Spring 2019

A routing study was completed in 2018 to determine the best route to connect the Houghton Road Active Transportation Corridor (ATC) to th

Phase 1 is an $86-million, three-year project that will separate the agricultural and domestic water systems in Southeast Kelowna.

Est. cost: $86 million
Est. start: Summer 2018
Est. end: 2021

Full width asphalt resurfacing with minor adjustment to pavement markings to widen the bike lanes.

KLO Road Bridge Replacement at Mission CreekFuture projects, Bike lanes, Roads

A conceptual design study is nearly complete for replacement of the Mission Creek Bridge at KLO Road. The study will also include potenti

This project will replace 400 metres of aging, vitrified clay pipe with polyvinyl chloride (PVC) pipe from Ethel Street to Gordon Drive.

Est. cost: $440,000
Est. start: Spring 2019
Est. end: Fall 2019

This project will replace 400 metres of aging infrastructure with polyvinyl chloride (PVC) pipe from Ethel Street to Gordon Drive.

Est. cost: $440,000
Est. start: Spring 2019
Est. end: Fall 2019