Infrastructure projects

We are continually working to create vibrant urban centres, a balanced transportation network and an inclusive community. Infrastructure projects focus on improvements and maintenance of outdoor spaces, buildings, active transportation networks, utilities, roads and bridges.

Navigate through the projects map below to find out what's coming up near you or filter by project type.

Subscribe to project updates     2018 Capital Projects at-a-glance

Significant investment throughout Kelowna boosts the local economy and builds the vibrancy of our growing city. Learn more about key projects within the city being constructed or managed by another organization.
 

Construction coming near your business? See the Open During Construction  resource for proactive planning tips.  

The southbound bike lane along Benvoulin Road at KLO Road will receive additional pavement markings for through movements.

Est. start: Summer 2018
Est. end: Fall 2018

Springfield Road To South Of Cooper Road

This project will add bike lanes on Bernard Avenue, between Lakeview Street and Ethel Street and will connect to the existing bike lanes

Est. start: Summer 2018
Est. end: Fall 2018

This project is to replace approximately 100 metres of 100 millimetre cast iron water main from 1956 with 150 millimetre polyvinyl chlori

Est. cost: $150,000
Est. start: Summer 2018
Est. end: Fall 2018

The current station has limited pump capacity and the existing structure prevents the upgrade to a larger pump and associated piping.

Est. cost: $110,000
Est. start: Fall 2018
Est. end: Winter 2018

Construction of a permanent, approximately 132 stall parking and informal drop-off area for Boyce-Gyro Park is planned this year on part

Est. cost: $2.195 million
Est. start: February 2018
Est. end: July 2018

Installation of an oil/water separator on Burtch Road to remove contaminants before storm water enters Mill Creek.

Est. cost: $90,000

Side mounted pedestrian flashers will be installed at the intersection of Lawrence Avenue and Burtch Road.

Est. cost: $30,000
Est. start: Summer 2018
Est. end: Fall 2018
Bus Stops Along Glenmore Drive Transit infrastructure

New bus stops will be added along Glenmore Drive heading to and from John Hindle Drive.

Est. cost: $25,000
Est. start: Spring 2018
Est. end: Summer 2018

Construction of a structure to catch sedimentation before the drainage water enters into Chichester Pond.

Est. start: Summer 2018
Est. end: Fall 2018